Thibodeau - Whole House

Jeff has asked that we transform his house and make it a place he can be happy in for some time. We will be building a large addition to the rear and side of the home comprising garage and storage on the ground floor, and a family room, master bath and bed on the second floor. The work inside and outside of the old house will make the whole thing appear new and will work with the new construction. The vaulted ceiling will give a huge feeling to the space and with the lot cleared, the new home will have a bright and breezy feel.

Thibodeau - Whole House

Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Future Plans - Representation and Drawing

Below is a gallery showing progress on this project day-by-day.

( Click on a preview to open a larger image )

Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 5 - The lot is cleared and we are ready to dig a hole...
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 9 - First there comes a hole... and a lot of dirty shoes
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 14 - Final day of digging and its getting tough to see where I am working... but it's nice to see level compacted footings ready for concrete
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 19 - Its nice to see stuff going back in the hole for once...
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 24 - Drains are in... all is nice and flat and square... tomorrow the lumber
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 29 - The walls are up, next comes the roof. Three more days with no rain would have it weathertight
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 34 - Two more days and it can rain... oops, just got 6 inches, ho hum
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 44 - We are weathertight, almost landscaped, electrical rough finished and plumbing and HVAC just started
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 50 - Inside rough is all finished, outside now since the weather is changing, then back inside
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 60 - Outside almost finished... then drywall and paint... couple of small things too like a shower, oh and bath... oh and fireplace... oh and...
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 65 - The wall board is almost finished, next comes the mud and the trim... heat will be on soon, and then the paint.
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 80 - Almost done, paint is going on, floors to put down and then boogie.
Thibodeau - Whole House Thibodeau - Whole House
Day 95 - The project is virtually finished, a few touches and time to move in properly
Thibodeau - Whole House Thibodeau - Whole House Thibodeau - Whole House
Day 100 - Flooring is almost complete... not by us... we are waiting for final inspections

Click here to download the Thibodeau - Whole House pictures